Before installation

• Note that the interior panels are meant only for indoor use and they must not be in direct contact with moisture. Interior panels are not suitable to be installed to the ceiling.
• Any faults in the materials shall be reported to prior to the installation. Large surfaces should be made of the same production batch.
• The batch number can be found on the bottom interior panel of the package.
• The interior panel suits only for premises where the room temperature and humidity are normal, approx. 20°C, and the relative humidity is approx. 40%, i.e. the walls and the ceiling of the room shall be dry with window glasses.
• The panel is not suitable for use with roof heating
• Interior panels should not be exposed to continuous temperatures of over 70°C.
• Please note the lighting manufacturer’s installation instructions concerning the temperature.
• The temperature and humidity of the interior panels shall be let to stabilise to the same temperature and humidity with the installation environment for three days before the installation. There is no need to open the packages completely, it is enough that you make a hole to the ends of the packages from where the humidity can be removed.

Background

• The distance between the joists should be max 300 mm (products 10x92, 10x120 and 10x160 max 400 mm), so the ceiling does not begin to ‘slouch’
• 315 mm wide panels must be installed parallel to the joists.
The recommended size for the joists is 45x45 mm, with a minimum of 20x40 mm.

• Make sure that there is sufficient air circulation behind the panels. If necessary, remove the bottom panels or attach reverse panels.
• Make sure that the bottom panels are straight, even if the ceiling is uneven.

Installation

• We recommend that you install the panels by using a stapling gun that is operated by compressed air. Use a staple that is at least 22 mm long, 11 mm wide and 1.6 mm thick.
• Shoot the staple diagonally into the long, protruding lower lip of the groove.
• To make installation of the panels possible, the staple must remain flush with the groove. The staple must not sink deep inside the groove, because then the panel will not be fastened properly.
• Leave at least 12 mm expansion gap between wall and the panels. If the slope exceeds the length or width of 6 meters, is expansion gap added 2 mm per exceeded meter.  The joint will be covered with fold molding /cornice.

Assembly

• You can affect the appearance of the ceiling by the way you position the seams of the grooves. You can make patterns in your ceiling by alternating the location of the end seams.

Safety

• Do not attach any light fittings or other heavy objects to the panel - instead, they should be attached directly to the mounting base.
• Observe the manufacturer's installation instructions concerning the temperature.

Maintenance instructions

Remove dirt and dust with a dry or slightly damp cloth, but avoid rubbing. To clean your ceiling, always use as little water as possible.
Never use boiling water for cleaning. If the stain does not just leave with the water, put a small amount of universal cleaner on the cloth. Do not use alkaline detergent.
Spray the cleaner on a clean cloth or moisten the cloth in another way.


The manufacturer will replace the defective product with a new equivalent product or the price of the defective product.

The manufacturer is not responsible for indirect costs.